PS Work Schedules
The Work Schedule step represents a collection of recurring operational delays. Work schedules can be created for various mining operational groups, such as Production and Development, to capture distinctive delay schedules.
The <Full Time> work schedule is a default schedule and can’t be edited.
To add a Work Schedule:
Press the blue plus icon.
Select the a field from the Name column and rename it, i.e. “Mining”.
To add Delays into the Work Schedule:
Select the applicable Work Schedule.
Press the blue plus icon.
Choose a delay from the Type dropdown list.
Configure the delay in the Configuration dropdown window.
Delays Configuration in the Configure dialog:
Section | Description |
---|---|
Recurring Delay | Untick if the delay is a singular occurrence |
Time of Day | Set the start time of the delay as well as the duration
|
Recurrence Setup | Daily - specify the recurrence at a daily granularity.
Weekly - specify the recurrence at a Weekly granularity.
Monthly - specify the recurrence at a Monthly granularity.
Yearly - specify the recurrence at a Yearly granularity.
|
Recurrence Range | The overarching duration in which the delay will be applied. Start date - specify the start date from which the delay will take effect. End Date:
|