PS Guidance Categories

Guidance categories in the Guidance Categories step are used to classify solids volumes by their mining date in the three month plan. For example, the categories “Two Week Plan”, “Three Month Plan”, “Out of Plan” could be used to classify dirt that is in the two week plan window, in the three month plan window, or out of plan respectively.

Guidance categories are later used for:

  • Colour-coding the reserves to make it easier to assign colors by numbers.

  • Reporting what categories are mined in each period.

Set Guidance Categories colors

Use the top toolbar buttons to:

  1. Add new item and remove item from the list,

  2. Move items up and down,

  3. Sort ascending and descending,

  4. Copy to Excel and Paste from Excel, and

  5. Clear all records, accordingly.

Note that when clicking the Paste from Excel button, all existing items from the list will be cleared.