ATS Increment Offset
Increment offsets may be used to force a minimum or maximum vertical lag between phases.Â
Every bench at elevation (E) in the Successor stage is made dependent on the bench at elevation (E+Offset) in the Predecessor stage. Offsets may be positive or negative.Â
To add an Increment Offset:
- Press the clipboard icon to add a new rule group.
- Rename the rule group (i.e. mining rules, backfill rules, land-bridge rules).
- Using the tree hierarchy on the right, select the successor record and double click on the predecessor.
- Set the Vertical Offset in metres:
- Negative to keep the successor elevated over the predecessor
- Positive to keep the predecessor elevated over the successor
- Verify the dependencies in the Preview panel.
Example of a 20 metre vertical lag between stages.
Cross-section showing the effects of Vertical Offsets on Stages.Â