3/12/2021 New 21.3 Release

3/12/2021 New 21.3 Release

Alastri is pleased to announce the release of v21.3.1053.


Alastri Production Scheduler

Improvements

  • Export Stage Plans for specific periods

    • It is now possible to export stage plans for selected periods. Previously when exporting stage plans, these could only be done for all periods, or for the current period.

APS: Export Stage Plans > Period Selection setting
  • Script Extensions - Extension Data Sources Validation Check

    • It is now possible to add a validation check for Extension Data Sources in the same way it is done for Extension Parameters.

  • Idle Time Report Fields

    • New fields Agent.Initial Productive Rate, Agent.Initial Nominal Rate, Agent.Operating Idle Hours and Agent.Operating Idle Factor are now available. Fields are available when creating Agent reports, and are also available in the Steady State tab.

    • Agent.Initial Productive Rate and Agent.Initial Nominal Rate represents the rate defined in the calendar for the current period.

    • Agent.Operating Idle Hours is calculated as the actual rate the agent operated at divided by the max rate at which the agent could have mined at.

    • Agent.Operating Idle Factor is Agent.Operating Idle Hours multiplied by the steady state duration.

Agent.Operating Idle Hours and Agent.Operating Idle Factor fields

Bug Fixes

  • Reporting

    • Fixed an issue where a crash occurred after docking the Reporting tab if a report was also undocked.

  • Schedule

    • Fixed an issue where the schedule failed to progress for certain projects.

  • Automated Dig Lines

    • Fixed an issue where dig lines created after running Automated Dig Line Creation tool were not being connected.


Alastri Tactical Scheduler

Improvements

  • Export Stage Plans

    • It is now possible to export stage plans for selected periods. Previously when exporting stage plans, these could only be done for all periods, or for the current period.

Bug Fixes

  • General

    • Fixed a crash occurring when closing certain projects after running the schedule.

    • Fixed a crash occurring when redocking a popped out report, after undocking and redocking the Reporting tab.

  • Infrastructure Reporting

    • Fixed an issue where Heritage items were not showing correctly in reports.

  • Long Term Stockpiles

    • Fixed an issue where only one phase was allowed to be mapped to a Long Term Stockpile.


Rapid Reserver

Improvements

  • Designer viewport

    • Added functionality to select all points under the cursor by Shift-Clicking when moving or deleting points in the Designer viewport. Similarly, using Shift-Click when adding points will add points to all construction lines under the cursor.

Bug Fixes

  • Designer

    • Fixed an issue where all walls of a block were not being selected correctly when clicking and dragging to select.

    • Fixed an issue where pressing “q” while using Create Polygon/Construction Line was changing the function to Quick Extend.


Spatial Conformetrics

Improvements

  • Export Stage Plans

    • It is now possible to export stage plans for selected periods. Previously when exporting stage plans, these could only be done for all periods.


All Products

Bug Fixes

  • Issues importing DXF Layers

    • Fixed an issue where layers were showing with zero triangles when certain DXF files were being imported as “Modern AutoCAD 2013 DXF”.

    • Fixed a crash occurring when importing certain DXF files that contained non-multiline text.

  • Layers panel

    • Fixed an issue where display options applied to a folder on the Layers panel were not saving with the project.


Haul Infinity

No specific changes for this release