Every project must have at least one crusher, which represents a transformation of an input material (such as mined tonnes) into an output material (such as product tonnes).

List of crushers used in a project is given in the Crushers step.

To add crushers:

  • Go to Haul Infinity > Designer tab:

    • find or create a crusher called "Crushers/CR1".

  • Go to back to APS > Setup tab > Site Lists step > Crushers field:

    • press the blue plus icon to add a crusher,

    • rename the crusher to "CR1".

  • Go to the Setup tab > Crushers step:

    • select a capacity field from the dropdown, such as “wetTonnes”. 

Crushers must be represented by a node in Haul Infinity. The node name must follow the convention “Crushers/myCrusherName”.