In the Setup > Wall Control Designs step, make visible only required categories and use the Painter tools to update the locations for each bench where the activity will be required. More details see here.
...
Designer tab
Once the Setup tasks are completed, go to the Designer tab and select one bench to visually inspect the results of your selections by selecting and bench and then one or many blocks where wall control is located.
...
In the Gantt, add/edit a sequence for the loader used to conduct Wall Scaling as per normal and schedule the batter blocks to be mined by the specified loader. Repeat the process for the Cable Bolting and Presplit Drilling agents.
...
Animations
Run your schedule and visually check the activities are being carried out before adjusting to suit.
...