Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 2 Next »

Custom dependencies set in the Custom step can be used to force precedence at any level of the block tree. This may be used to enforce a certain order of pit development, land bridge precedence and/or backfill permissions. 

To add a custom dependency:

  1. Press the Blue Plus icon to add a new dependency set.

  2. Rename the dependency set (i.e. mining rules, backfill rules, land bridge rules).

  3. Using the tree hierarchy on the right, select the successor record and double click on the predecessor.


Раздел документации на русском языке 🇷🇺

  • No labels