PS Preschedule

In the Preschedule step set the proportion remaining to drill, charge, or mine.

Set the ratio remaining in each activity, in each record

Preschedule step screen elements are listed below.

Field

Usage

Field

Usage

Proportion Remaining

The percentage remaining in every sum field for the selected activity

Remaining

The quantity of the field selected in the Display Field dropdown list after preschedule has been applied

Total

The quantity of the field selected in the Display Field dropdown list before preschedule has been applied

Delays (days)

The number of days before the selected activity can proceed on a record.

Example: At the beginning of the plan, a blast may be halfway through pattern prep. A delay can be used to represent the remaining duration of the prep time, preventing the blast from being drilled straight away.

See different options of prescheduling below.

Single Record Preschedule

  1. Select an activity from the Activity list.

  2. Expand the record tree to the blast or dig solid.

  3. Set the proportion remaining.

Bulk Preschedule

  1. Select an activity from the Activity list.

  2. Expand the record tree to a given level.

  3. Right click > “Set Values to …” option > (amount remaining).

Bulk prescheduling to a set value

Automatic Preschedule from Surface

  1. Press Use Surface button.

  2. Select preschedule surface, records to check and activities to preschedule in a Preschedule with Surface dialog.

Graphical Preschedule

  1. Click Edit Graphically button.

  2. In the Reserves Shading field dropdown select “<Proportion Remaining (Activity)>” option.

  3. Select one or more blocks for prescheduling.

  4. Right click > “Specify Remaining Value for Selected Blocks” option > enter new value in a dialog > OK.

Manually prescheduled elements are shown in green bold in the tree hierarchy.

Blocks set for mining as 0 remaining, will appear in graphics with 0 tonnes and 0 bcm. To remove completely use the Record Removal step.

Prescheduling does not recognise where material is spatially, just that a % of the block has been mined and the inventory of all parcels is reduced by that %. It is recommended that mining prescheduling with a depletion surface is done in Rapid Reserver which will remove material from the correct location spatially.