TS Phase Adjacencies

Phase Adjacencies prevent underground mining and underground dumping. For example, you can mine Cutback1 and Cutback2 simultaneously, but Cutback2 cannot under-cut Cutback1. Similarly you can backfill a pit while it is being mined, but you can't dump underneath an unmined block.

Phase Adjacencies only set vertical dependencies between blocks. To finish an entire stage before another, see Custom Dependencies

Phase Adjacencies step overview

Description of this step columns, see below.

Name

Above Stages

Inner Stages

Dump -> Pit Standoff

Name

Above Stages

Inner Stages

Dump -> Pit Standoff

List of all the scheduling elements arranged in the tree level hierarchy Mine/Pit/Stage/Bench/Flitch or Dumps/Dump/Lift or Backfills/Pit/Bench. Click on a parent level to expand children levels.

“Above Stages” should be used where there is a stage, and above it, there is another stage, but it is not nested inside. So if A is set to be an above stage of B, in order to mine a block in B, you would need to mine a block in A on the bench above.

“Inner Stages” should be used where if there are nested pits A and B, where A is inside B, you would set A as an inner stage for B. In order to mine a block in B, you would need to mine a block in A that is at the same RL.

Set standoff distance between a dump and a pit

Phase Adjacencies types