PS. Equipment Rosters

Each piece of equipment needs to be paired with a work schedule in the Equipment Rosters step. The work schedule delays and maintenance delays result in an overall Equipment Roster.

Equipment Rosters step overview

To generate an Equipment Roster:

  1. Select a piece of equipment from the Equipment Name/Type lists.

  2. Select applicable work schedule from the Schedule dropdown list.

  3. Check the calendar timeline to ensure delays are correct.

    • Hover the delay bar to display delay information.

    • Toggle Show Maintenance Delays and Show Fixed Delays flags on and off to simplify the view.

You can use multi-selection function (<CTRL> or <SHIFT> keys) to quickly apply the same work schedule to the related equipment, such as production diggers or blasting equipment.