APS Scenarios

The scenarios panel contains the scenario modes, scenario list, and run button.

  • Run a drill schedule, dig schedule, or both.

  • Merge schedules from two users.

  • Use scenarios to ‘save as you go’.

  • Use scenarios to test doing something different.

Schedule > Scenarios panel.

Date

The top of the Scenarios panel displays the date and time of the current slider location.

Run Buttons

Press the first blue play icon to run a single period of the schedule, this will be either the earliest period that has changes, or the next unscheduled period if there have been no changes.

The second play icon, will run the highlighted scenario.

The third play icon, will run all scenarios.

Green progress bars show the scenario schedule state.

All Scenarios will be using the same project setup parameters, each can have custom inputs in the Calendar, Gantt and animation.

Scenario Mode

Each scenario can be run in three modes.

  • ‘Mining Mode’ ignores drilling dependencies. Use this mode to run a digger-only schedule.

  • ‘Ancillary Mode' is used to align the ancillary sequences to the Mining Mode.

  • ‘Everything Mode’ enforces all dependencies. Use this mode to schedule diggers and drills together.

A green progress bar indicates how much of the schedule has been run. Yellow highlighting indicates the schedule has been invalidated past that point (by a move on the Gantt).

 

Animations and Reports show results for the selected mode.

Scenarios

Each scenario runs a schedule based on the inputs in its Calendar, Gantt, and Animation.

Scenario controls.

‘Save points’ can be created by copying a schedule, locking the original, and working on the copy.

Merge Scenarios

Scenarios can be merged if you have two people working in parallel. See Merge Scenarios

Right click > Merge With > other scenario.

Choose which items to merge from both scenarios.

Performance Profiler

The performance profiler allows experts to diagnose performance issues in the project. Each line item reports the time taken on that task during the schedule.

Performance profiler view.

Slow Haulage

If haulage is taking a long time, consider reducing the number of auto-joins in Haul Infinity, or the number of available dumps in the Destination Rules.