PS. Stockpile Build Settings
In the Stockpile Build Settings step user can configure stockpile settings.
Setting | Usage |
---|---|
Mutex Group | Stockpile Mutex Group |
Preferred Build Order | Preferred Build order for all stockpiles in a Group. Can set the order stockpiles are built. |
Starting Build Number | Stockpile builds will count up from this number |
Maximum Number of Builds | This field is restricted to Single-Mutex, Single-Counter, Build Target stockpiles. |
Size | The capacity of the stockpile. |
Minimum Size to Reclaim | This field is restricted to Mutex Group stockpiles. |
Minimum Size to Refill | This field is restricted to Mutex Group stockpiles. |
State Change Triggers New Reclaim Decisions | Enable to initiate new reclaim decision when stockpile state changes |
Build to reclaim Delay (h) | Time delay between stockpile building end and reclaiming start, in hours |
Reclaim to Build Delay (h) | Time delay between stockpile reclaiming end and building start, in hours |
Non Mutex stockpiles can have Turnover Triggers set in the Calendar. Allowing them to be switched to the Reclaim mode before reaching capacity.
Within APS, a new stockpile build is triggered when all of the material from the stockpile has been depleted. If a stockpile switches to build mode before all of the material has been reclaimed, the build number will remain the same until all of the material from the stockpile has been depleted. In the Stockpile Builds report, the values shown for a particular build will be for the point in time where the build encountered its highest peak. This logic can be seen in the image below.