TS. Plant Grades Failing
Follow these steps when the crusher is feeding, but for some reason the grades are out of acceptable limits.
If the schedule has one of below listed issues, resolve them first:
Check 1: Setup > Map Fields > Parcel Mappings
Make sure that tonnes and grades are mapped in all Mining and Processing fields. Missing mappings are evaluated as zeroes, which may affect the optimisation.
Check 2: Reserves tab > Data panel
Do a quick sanity check in the Reserves tab on the schedule inventory. Sometimes the block model has errors, or there may be incorrect call factors in Setup > Refinements.
Check 3: Setup > Opening Inventories
Make sure that tonnes and grades are populated in all Mining and Processing fields. Missing entries are evaluated as zeroes, which may affect the optimisation.
Check 4: Schedule > Calendar > Stockpiles
Stockpiles may be forced to reclaim material if the closing capacity is less than the opening inventory. This can cause otherwise rubbish material to be forced into the feed, and contaminate the grades.
Check 5: Schedule > Calendar > Constraints
Good material may be blocked from the crusher if there are constraints on feed. This can cause otherwise rubbish material to make up the difference.
Always check the constraint configurations in Setup > Constraints > Configuration. It is extremely common to see mistakes in the setup have domino effects in the schedule.
Check 6: Schedule > Calendar > Product Specifications
Check for unachievable or conflicting product specifications.
See TS. Product Specifications for tips on correct setup.
Check 7: Schedule > Reporting > Mined grades and inventories
Check mined grades and closing stockpile inventories.
If the available tonnes do not meet product specifications, then either change the mining locations or relax the product limits to allow feed.
Check 8: Schedule > Calendar > Forced Optimisation Failure
Create a forced optimisation failure and read the failure message.
Go to Setup > Constraints and constrain all movements except for the expected movement.
Go to Calendar > Constraints and zero the constraints to force material into the expected path.
Run the schedule.
Read the failure message.