PS. Preschedule
In the Preschedule step set the proportion remaining to drill, charge, or mine.
Screen Elements
Preschedule step screen elements are listed below.
Field | Usage |
---|---|
Proportion Remaining | The percentage remaining in every sum field for the selected activity |
Remaining | The quantity of the field selected in the Display Field dropdown list after preschedule has been applied |
Total | The quantity of the field selected in the Display Field dropdown list before preschedule has been applied |
Delays (days) | The number of days before the selected activity can proceed on a record. Example: At the beginning of the plan, a blast may be halfway through pattern prep. A delay can be used to represent the remaining duration of the prep time, preventing the blast from being drilled straight away. |
Legend
See the Colors Legend in the bottom left-hand corner of the Preschedule step, which helps understand the meaning of the text colors.
Prescheduling
See different options of prescheduling below.
Single Record Preschedule
Select an activity from the Activity list.
Expand the record tree to the blast or dig solid.
Set the proportion (or volume) remaining.
Manual Values will be displayed Bold Orange (as per Legend in the Activity panel).
Bulk Preschedule
Select an activity from the Activity list.
Expand the record tree to a given level.
Right click > “Set Values to …” option > (amount remaining).
Preschedule options
Use the dropdown menu available through the right mouse click to:
Set all values for the selected record to 1.
Set all values for the selected record to 0.
Set all values for the selected record to the proportion specified.
Clear Proportion Values set manually.
Clear Proportion Values set automatically.
Clear Values set for Delays.
Graphical Preschedule
Click Edit Graphically button.
In the Reserves Shading field dropdown select “<Proportion Remaining (Activity)>” option.
Select one or more blocks for prescheduling.
Right click > “Specify Remaining Value for Selected Blocks” option > enter new value in a dialog > OK.
Automatic Preschedule from Surface
Press Use Surface button.
In the Preschedule with Surface dialog choose Surface to use for prescheduling, min/max Thresholds, Records to check and Activities to preschedule .
Clearing Preschedule Data
To clear all manual or automatic prescheduled data, right-click on an activity in the Activity panel and select “Clear Preschedule Data for <Activity>”. All the Preschedule data will be removed and records color return to standard.
Notes
Blocks set for mining as 0 remaining, will appear in graphics with 0 tonnes and 0 bcm. To remove completely use the Record Removal step.
Prescheduling does not recognise where material is spatially, just that a % of the block has been mined and the inventory of all parcels is reduced by that %. It is recommended that mining prescheduling with a depletion surface is done in Rapid Reserver which will remove material from the correct location spatially.