PS Activity Sequences
An Activity Sequences step can be used to set logical dependencies between activities, i.e., you can’t mine a blast until it has been drilled and blasted. These can be constrained to a particular record set, defined by the user.
Subsets created in the Setup tab > Record Subsets step are available to be used here.
Column | Description |
---|---|
Records | Select record subsets to apply the following dependency to |
Successor | The activity to follow the predecessor activity |
Predecessor | The activity to be completed before the successor activity |
Delay (h) | A delay, specified in hours, which will be applied to the successor activity once the predecessor activity has been completed |
To add an Activity Sequence:
Press the blue plus button.
Configure the sequence as per table above.
Activity Sequences can be added through scripts. These entries in the table will appear in bold blue and can’t be edited.