PS Work Schedules
A work schedule represents a collection of recurring operational delays. Work schedules can be created for various mining operational groups, i.e., Production and Development, to capture distinctive delay schedules.
Setup > Work Schedules.
The <Full Time> work schedule is a default schedule and can’t be edited.
To add a Work Schedule:
Press the blue plus icon.
Select the Name field and rename it – i.e. Mining.
To add Delays into the Work Schedule:
Select the applicable Work Schedule
Press the blue plus icon.
Choose a delay from the drop-down list.
Configure the delay
Delay Configuration:
Section | Description |
---|---|
Recurring Delay | Untick if the delay is a singular occurrence. |
Time of Day | Set the start time of the delay as well as the duration.
|
Recurrence Setup | Daily - Specify the recurrence at a daily granularity.
Weekly - Specify the recurrence at a Weekly granularity.
Monthly - Specify the recurrence at a Monthly granularity.
Yearly - Specify the recurrence at a Yearly granularity.
|
Recurrence Range | The overarching duration in which the delay will be applied. Start date - Specify the start date from which the delay will take effect. End Date
|