PS Work Schedules

A work schedule represents a collection of recurring operational delays. Work schedules can be created for various mining operational groups, i.e., Production and Development, to capture distinctive delay schedules.

Setup > Work Schedules.

The <Full Time> work schedule is a default schedule and can’t be edited.

To add a Work Schedule:

  1. Press the blue plus icon.

  2. Select the Name field and rename it – i.e. Mining.

To add Delays into the Work Schedule:

  1. Select the applicable Work Schedule

  2. Press the blue plus icon.

  3. Choose a delay from the drop-down list.

  4. Configure the delay

Delay Configuration:

Section

Description

Section

Description

Recurring Delay

Untick if the delay is a singular occurrence.

Time of Day

Set the start time of the delay as well as the duration.

 

Recurrence Setup

Daily - Specify the recurrence at a daily granularity.

 

Weekly - Specify the recurrence at a Weekly granularity.

 

Monthly - Specify the recurrence at a Monthly granularity.

 

Yearly - Specify the recurrence at a Yearly granularity.

 

 

Recurrence Range

The overarching duration in which the delay will be applied.

Start date - Specify the start date from which the delay will take effect.

End Date

  • No end date - The delay will continue throughout the schedule.

  • End after - Choose to end the delay after several occurrences.

  • End by - Hard end date for the delay.