PS Equipment Rosters

Each piece of equipment needs to be paired with a work schedule. The work schedule delays and maintenance delays result in an overall Equipment Roster.

Setup > Equipment Rosters.

To generate an Equipment Roster:

  1. Select a piece of quipment from the list.

  2. Select applicable work schedule from the drop-down list.

  3. Check the calendar timeline to ensure delays are correct.

    • Hover of the delay bar to display delay information.

    • Toggle work schedule delays and maintenance delays on and off to simplify the view.

Use multi-select to apply the same work schedule to related equipment, i.e., production diggers, blasting equipment.